Implementing Brellium takes ~10 hours of your team’s time to go from contract signing —> production. Our engineering team handles the heavy lifting and walks side-by-side with you throughout the process.
If your team wants to move quicker, ask your Account Manager if we can accommodate. The quickest go-live we’ve done is 4 days from contract signing.
Project Team:
- Clinical / Quality Lead
- Quality Assurance Team
- IT Team
Phase 1: Pre-Contract
Time spent by your team: 4 hours
- Infrastructure Assessment
- Evaluate your existing IT infrastructure, including EMR access, and determine if any upgrades or changes are necessary to support Brellium.
- Develop plan to port session note data to Brellium.
- Contract Signing
Phase 2: System Configuration and Testing
Duration: 16 days (if it is our first time supporting your EMR/PMS, go-live is extended for 4-6 weeks)
Time spent by your team: 3 hours
-
Customization Meeting (Day 1)
Brellium - Implementation Meeting
- Your operations team and Brellium’s engineering team meet to line-by-line through your session notes and question sets.
- Ensure screening, reporting, and workflow built to your specifications.
-
Data Integration (Days 2-14)
- Integrate Brellium with your EMR.
- Handled by Brellium’s engineering team.
- Note: if Brellium already integrates with your EHR, this does not need to be done
- Ensure data security and compliance.
- Ensure criteria are being enforced accurately on a large sample of audits (no charge)